140 crores rupees spent for 600 Watersheds in Bolangir

 An amount of Rs. 140 crores 
spent  in Bolangir district,
Odisha  for construction of 600   Watersheds 
within 14 years without  single  increase 
in percentage of irrigated 
land  in the  district (!)  , exposed through RTI

Bolangir was infamous and still infamous  as one  of the most drought prone districts in the 
country and  for its
notoriety  of  large scale migration, hunger and  starvation death. Both the Central Govt. and
State Govt. have undertaken numerous schemes, anti-poverty programme,
food security programme in order to
ensure food security and increase living
standard  of the poor and vulnerable  families in the district. Watershed Project is one of the programme  undertaken 
with allocation of  huge  fund 
to  increase  ground water table with water  conservation measures, ensuring  irrigation to lands, providing
employment to the people  through 
developing agriculture and horticulture activity etc. It is a multi-pronged approach  to end poverty, ensure food security and
reduce migration in Bolangir. Both
Govt agencies and NGOs were engaged to undertake watershed projects in the
district.  

RTI Application was submitted
in December, 2014 to the PIO, office of Project Director, watershed, Bolangir
seeking information about details of Watershed projects undertaken under different
scheme in Bolangir and the amount spent for it from beginning to 2014.  The information provided by the PIO is as
follows.

Sl. No
Name of the
Scheme
No. of
Watershed
       Project Period
Expenditure
incurred ( In lakh)
From
To
1
Employment Assurance Scheme
91
1998-99
2005-06
1741.51
2
ACA ( RLTAP)
28
2002-03
2010-11
756.55
3
Spl RLTAP (ACA)
10
2008-09
2011-12
332.94
4
IWDP-II
19
1997-98
2011-12
483.43
5
IWDP-III
6
2000-01
2011-12
199.93
6
IWDP-IV
10
2006-07
2011-12
198.59
7
IWDP-V
10
2006-07
2011-12
213.32
8
DPAP ( 6th
Batch)
20
2000-01
2011-12
600.00
9
DPAP ( 7th
Batch)
32
2001-02
2010-11
306.00
10
DPAP (8th Batch)
32
2002-03
2010-11
277.32
11
DPAP (9th Batch)
32
2003-04
2010-11
138.56
12
DPAP (10th
Batch)
32
2004-05
2010-11
143.79
13
DPAP (11th
Batch)
36
2005-06
2011-12
832.83
14
DPAP (12TH
Batch)
36
2006-07
2011-12
798.10
15
WORLP (PY-I)
4
2000-01
2004-05
190.00
16
WORLP (PY-II)
16
2001-02
2005-06
760.00
17
WORLP (PY-III)
32
2002-03
2006-07
1505.23
18
WORLP (PY-IV)
40
2003-04
2007-08
1880.77
19
WORLP (PY-V)
32
2004-05
2008-09
1497.63
20
WORLP (PY-VI)
16
2005-06
2009-10
748.82
21
IWMP-I
10
2009-10
2011-12
96.70
22
IWMP-II
12
2009-10
2011-12
122.29
23
IWMP-III
10
2009-10
2011-12
98.06
24
IWMP-IV
9
2009-10
2011-12
87.26
25
IWMP-V
10
2010-11
2011-12
40.96
26
IWMP-VI
12
2010-11
2011-12
51.71
27
IWMP-VII
9
2011-12
2011-12
24.77
28
IWMP-VIII
9
2011-12
2011-12
22.00

Total
615


14149.16


(ACA– Additional Central Assistance, IWDP– Integrated Watershed Development Project, WORLP– Western Odisha Rural Livelihood Mission
supported by DFID, UK, DPAP– Drought Prone Area
Programme, IWMP-Integrated watershed Management
Programme)

Pradip Pradhan, RTI Activist
Odisha Soochana
Adhikar Abhijan
M-9937843482

Date- 31.07.2015