Status of Mega
Drinking Water Projects undertaken by non-Odia Contractors in different districts,
Odisha
(Information
obtained under RTI Act by May 2025)
In 2023, the information
received under RTI Act from Govt. Departments ( https://odishasoochana.blogspot.com/2023/12/non-odia-contractors-awarded-huge-work.html ) exposed how a
mega Drinking water project worth
thousands of crores of rupees
have been designed to hand over the
non-Odia Contractors. A total amount of Rs 35,000 crores was simply
handed over to 17 Non-Odia Companies who enjoy patronage of Sri V.K. Pandian,
the then Secretary to former Chief Minister and his close associates i.e, non-Odia officers in Odisha
bureaucracy. During that time, we
had alleged that these mega Projects
handed over to non-Odia Contractors and
sidelining Odia Contractors was meant to loot state exchequer in name of
providing drinking water to the People of Odisha. After
BJP Govt. came to power in 2024, we filed complaint before Govt. seeking an
inquiry and special audit into allotment of mega projects to all non-Odia
Contractors. Despite assurance given by
Govt., no inquiry was conducted so far.
Out of our curiosity and to understand the status of the project and
action, if any taken by Govt. against Non-Odia Contractors, we filed RTI in the
office of Engineer-in-Chief, RWSS to access this information. The below is the
present status of the mega drinking
water projects. Though four to
five years passed since sanction of the project and despite extension of
time is granted, not a single project has been completed so far. The lack of
potable drinking water for rural people
in Odisha has led to widespread outbreak of Diarrhoea in different
districts. We put this information in
public domain with the objective generating public opinion and putting pressure
on Govt. to refrain from sanctioning any kind of project to non-Odia
Contractors.
|
Sl.No. |
Name of District |
Name of agency |
Name of the project |
Total amount sanctioned with |
Total amount utilized |
Status of the project |
Remarks |
|
1 |
Puri |
M/s Indian Hume Pipe Co. |
Mega Piped Water Supply to |
Rs. 192.46 crore in 2023 |
NA |
On-going |
|
|
2 |
Puri |
M/s Indian Hume Pipe Co. |
Mega Drinking Water Project |
Rs. 213.98 crore |
NA |
On going |
|
|
3 |
Puri |
M/s Indian Hume Pipe Co. |
Mega Drinking Water Project for water supply to 78 villages of Delang Block |
Rs. 107.42 Crore |
NA |
On4 going |
|
|
4 |
Puri |
M/s GVPR Engineer’s Co |
Mega Drinking Water Project for water supply to 126 villages of Kanas |
Rs. 184.12 Crore |
NA |
Ongoing |
|
|
5 |
Khorda |
JMC-Jindal water |
Piped Water Project to 337 |
Rs. 326.08 Crore |
NA |
On going |
|
|
6 |
Khorda |
Krishan S, Mumbai and UMSL Ltd, Odisha |
Mega PWS to Ranipada Cluster |
Rs. 67.57 Crore |
NA |
Ongoing |
|
|
7 |
Khorda |
L &T Company |
Mega PWS to Chilika, Tangi and Banpur blocks |
Rs. 188.76 Crore |
NA |
Ongoing |
|
|
8 |
Khorda |
L and T Company |
Mega PWS to Begunia and |
Rs. 278.06 Crore |
NA |
Ongoing |
|
|
9 |
Khorda |
NCC Company |
Mega PWS to Balipatna Block |
Rs. 142.73 Crore |
NA |
Ongoing |
|
|
10 |
Khorda |
NCC Company |
Mega PWS to 16 GPs of |
Rs. 128.62 Crore |
NA |
Ongoing |
|
|
11 |
Khorda |
NCC Company |
Mega PWS to 9 GPs of |
Rs. 82.61 Crore |
NA |
Ongoing |
|
|
12 |
Khorda |
NCC Company |
Mega PWS to 6 GPs of |
Rs. 46.72 Crore |
NA |
Ongoing |
|
|
13 |
Khorda |
NCC Company |
Mega PWS to 17 GPs of Tangi |
Rs. 133.58 Crore |
NA |
Ongoing |
|
|
14 |
Jajpur |
Megha Engineering and |
Mega PWS to Dasarathpur Block |
Rs. 181.78 Crore , |
Es. 158.95 crore |
On going |
Project was about to be completed by 30.12.2021 . |
|
15 |
Jajpur |
Megha Engineering and |
Mega PWS to Badachana Block |
Rs.335.72 Crore sanctioned |
Rs. 287.32 crore |
On-going |
Project was about to be completed by 30.12.2021 . |
|
16 |
Jajpur |
Megha Engineering and |
Mega PWS to Dharmashala |
Project was about to be completed by 30.12.2021 . |
|||
|
17 |
Jajpur |
Megha Engineering and |
Mega PWS to Jajpur and |
Rs.245.98 crore , sanctioned |
Rs.189.18 crore |
On-going |
Project was about to be completed by 22.3.24 . But EOT applied upto 24.3.25 Still |
|
18 |
Jajpur |
KEC and BRCC |
Mega PWS to Danagadi block |
RS. 87.11 Crore |
Rs. 67.35 crore |
On going |
Project to be completed by |
|
19 |
Jajpur |
KEC International Ltd joint |
Mega Drinking Water Project |
Es.167.16 crore |
Rs. 115.77 crore |
On going |
Project to be completed by |
|
20 |
Jajpur |
KPIL |
Mega PWS to 258 villages |
Rs.127.06 crore |
Rs. 32.79 crore |
On going |
The project is about to be |
|
21 |
Jajpur |
KPIL Company |
Mega Drinking Water Project |
Rs. 127.60 crore Sanctioned on 2022-23 |
Ongoing |
||
|
22 |
Jajpur |
NCC Limited |
Mega Drinking Water Project |
Rs. 107 crore sanctioned in |
Rs. 101.09 crore |
Ongoing |
Project was sanctioned on |
|
23 |
Jajpur |
NCC Limited |
Mega Drinking Water Project |
Rs. 79.56 crore sanctioned in 2017-18 |
Rs. 67.03 crore |
Ongoing |
Project was about to |
|
24 |
Jajpur |
NCC Limited |
Mega Drinking Water Project for 15 no. of |
Rs. 46.19 crore sanctioned |
Rs. 43.99 crore |
Ongoing |
Project was about to |
|
25 |
Rayagada |
M/S KEC Limited and SPML Joint Venture |
Mega Drinking Water Project |
Rs. 298.70 crore |
Rs. 152.20 crore |
On-going |
No action taken |
|
26 |
Rayagada |
M/s Zuberi Engineering |
14 GPs of Gunupur Block |
Rs. 79.40 Crore |
Rs. 58.40 Crore |
On-going |
No Action Taken against the Company |
|
27 |
Rayagada |
M/S SIIPL and SIEPL Joint |
3 no. Individual RPWS |
Rs. 114.68 Crore |
Rs. 35.58 Crore |
On-going |
No action taken against the Company. |
|
28 |
Rayagada |
M/s Zuberi Engineering |
Execution of Mega PWS |
Rs. 84.23 Crore |
Rs. 63.37 Crore |
On-going |
No action taken by the |
|
29 |
Cuttack |
M/s Megha Engineering |
Mega PWS Project for 37 GPof |
Rs. 194.92 Crore |
Rs. 165.95 Crore |
On-going |
Partially functional |
|
30 |
Cuttack |
Blue Star , SPML Infra JV Limited |
Mega PWS Project for 72 villages of Nischntakoili Block |
Rs. 62.16 Crore |
Rs. 26.67 Crore |
Ongoing |
Non-Functional |
|
31 |
Cuttack |
Blue Star VISHWA Infra JV |
Executing of Mega PWS |
Rs. 189.69 Crore |
Rs. 68.64 Crore |
Ongoing |
No-functional |
|
32 |
Cuttack |
M/S Dineshchandra R. Agrawal |
Execution of PWS Project for |
Rs. 153.51 Crore |
Rs. 27.16 Crore |
Ongoing |
Non-functional |
|
33 |
Gajapati |
JMC – SPML Joint Venture |
Mega PWS Project for 39 GP |
Rs. 622.13 Crore |
Rs.198.57 Crore |
Ongoing |
|
|
34 |
Gajapati |
Mega PWS Project for 19 GPs |
|
|
|||
|
35 |
Gajapati |
5 GPs of Gumma Block |
Rs.30.33 Crore |
|
Ongoing |
|
|
|
36 |
Gajapati |
Megha Engineering and |
Mega PWS project for 190 |
Rs. 379.17 Crore |
Rs. 47.88 Crore |
ongoing |
|
|
37 |
Boudh |
Land T Company Ltd. |
Mega PWS Project for Boudh |
Rs.205.48 Crore |
Rs. 194.89 Crore |
Ongoing |
|
|
38 |
Boudh |
Land T Company Limited |
Mega PWS Project for |
Rs. 214.93 Crore |
Rs.202. 22 Crore |
Ongoing |
|
|
39 |
Boudh |
Land T Company Limited |
Mega PWS Project for Harabhanga Block |
Rs. 195.70 Crore |
Rs. 134.47 Crore |
Ongoing |
|
|
40 |
Nawarangpur |
JMC-JWIL Company |
Mega PWS project for 72 GPs |
Rs. 149.39Crore sanctioned |
Rs.139.20 Crore |
Ongoing |
Date of the |
|
41 |
Nawarangpur |
JMC-JWIL Company |
Mega PWS project for 11 GPs |
Rs. 99.01 Crore sanctioned on 9.8.2019 |
Rs. 101.63 Crore |
Ongoing |
Date of the |
|
42 |
Nawarangpur |
M/s GVPR Engineering Pvt. |
Two no. Individual Mega PWS |
Rs. 403.94 Crore sanctioned |
Rs. 368.41 Crore |
Ongoing |
The Project was about to |
|
43 |
Nawarangpur |
M/s GVPR Engineering Pvt. |
Two no. Individual Mega PWS |
Rs. 139.48 Crore sanctioned on 1.3.2019 |
Rs.118.73 Crore |
Ongoing |
|
|
44 |
Nawarangpur |
M/s L and T Company Ltd |
66 villages of Dabugaon |
Rs. 261.27 Crore |
Rs.39.04 Crore |
Ongoing |
The project started on 294.23 and date fixed |
|
45 |
Keonjhar |
M/s NCC Ltd, Hyderabad |
19 villages under Hatadihi |
Rs.35.87 Crore |
Rs. 36.15 Crore |
Completed and operational |
|
|
46 |
Keonjhar |
M/s NCC Ltd, Hyderabad |
200 villages under Hatadihi |
Rs. 281.87 Crore |
Rs. 290.08 Crore |
Ongoing |
Though more amount released |
|
47 |
Keonjhar |
M/s Megha Engineering |
Mega PWS for 138 no. |
Rs.182.32 Crore |
Rs. 186.18 Crore |
Ongoing |
Govt. has penalized / |
|
48 |
Keonjhar |
M/s Megha Engineering |
Mega PWS to 81 no. villages |
Rs.112.37 Crore |
Rs. 114.62 Crore |
Ongoing |
Govt. has penalized / |
|
49 |
Keonjhar |
M/s Megha Engineering |
Mega PWS to 200 no. |
Rs. 155.44 Crore |
Rs. 151.12 Crore |
Ongoing |
Govt. has penalized / |
|
50 |
Keonjhar |
M/S Land T limited |
Mega PWS for 144 |
Rs. 1176.50 sanctioned in |
Rs. 355 .53 Crore |
Ongoing |
The Govt. Has imposed |
|
51 |
Sundargarh |
Kalpataru Pvt. Ltd ( JMC) |
Mega PWS for Bisra, Lathikata, Lahunipada and Bonai block |
Rs.388.81 Crore |
Rs. 215.44 Crore |
Ongoing |
60% work completed . Govt. |
|
52 |
Sundargarh |
Universal MEP Project and |
Mega PWS to Gurundia and |
Rs. 152.00 crore |
Rs. 121.74 crore |
Ongoing |
An amount of |
|
53 |
Sundaragarh |
Universal MEP Project and |
Mega PWS for Koida and |
Rs.168.11 Crore |
Rs. 121.74 crore |
Ongoing |
A penalty amounting Rs. 30, |
|
54 |
Sundaragarh |
Universal MEP Project and |
Mega PWS for Kuanrmunda, |
Rs. 340.39 Crore |
Rs.282,09 Crore |
Ongoing |
Rs. 19,31,910 penalty |
Prepared
by Pradip Pradhan , M-9937843482
Date-
25.6.25